ITEM 5 - PUBLIC PARTICIPATION - CODICOTE TRANSPORT PLAN
1. Presentation of a petition
2. Response by a representative of Codicote Parish Council
ITEM 6 - CODICOTE TRANSPORT PLAN PROPOSED PELICAN CROSSING
Report of the Strategy Manager Hertfordshire Highways
To update the JMP on the provision of schemes within the Codicote Parish Plan and seek JMP approval for the proposed pelican crossing.
Item 6. - Codicote Transport Plan
ITEM 7 - LUTON ROAD, COCKERNOE - HIGHWAY IMPROVEMENTS
District Councillor Tom Brindley
This item will be in the format of an oral presentation
ITEM 8 -ITEMS REFERRED FROM NHDC AREA COMMITTEEE TO THE JMP
To consider any proposals for traffic managment schemes that could be joint matched funded with the JMP Discretionary Budget for 2008-2009 and other items of interest raised in the recent cycle of NDC Area Committee meetings.
Item 8 - Refferrals to the JMP
ITEM 9 - PAYNES PARK, HITCHIN, - GYRATORY ACCESS IMPROVEMENT
Report of the Strategy Development Manager, Hertfordshire Highways
To advise the JMP on the access improvements to Paynes Park gyratory in two phases- 2008-2009 and following funding in 2009-2010.
ITEM 10- DEVELOPER SECTION 106 HIGHWAY CONTRIBUTIONS UPDATE
Report of the Highways Development Control Services Manager
Item 10 - Section 106 Obligations
ITEM 11- LETCHWORTH GATE AND JUNCTION 9 OF A1(M)
Report of the Technical Standards and Programmes Manager, Hertfordshire Hhighways
A response to the request by JMP at the meeting held on 23 June 2008 for the feasibility of investigations as to the viability and cost of installation of additional traffic signals at the north bound slip at Junction 9 of the A1(M).
ITEM 12- 2008-2009 INTEGRATED WORK PROGRAMME DELIVERY - UPDATE
Report of the Lead Assistant District Manager, Hertfordshire Highways
To update the JMP on the delivery of the Integrated Work Programme for 2008- 2009 within North Hertfordshire
Item 12 - 2008-2009 Integrated Work Programme
v
ITEM 13- INTEGRATED WORK PROGRAMME 2009-2010 AND FORWARD WORK PROGRAMME 2010-2014 - DRAFT 2
Report of the Principal Strategy Development Manager, Hertfordshire Highways
To present to the JMP the second draft of the IWP highway shemes planned for implementation within the local area in 2009 -2010 and the forward works programme of schemes planned for 2010 - 2011 to 2013 - 2014.
Item 13 - Forward IWP 2009-2010 to 2010 to 2014
ITEM 14- JOINT MEMBER PANEL DISCRETIONARY BUDGET
Report of the North Herts District Manager, Hertfordshire Highways
To recommend to the JMP possible schemes for funding in 2008-2009 and to update the JMP on issues raised by the NHDC Area Committees
Item 14 - Joint Member Panel Discretionary Budget
ITEM 15 - OPERATIONAL PERFORMANCE INDICATORS
Report of the North Herts District Manager
To advise the JMP of the performance of Hertfordshire Highways for the inclusive period March 2008 - August 2009.
Item 15 Operational Performance Indicators ![]()